Projects implemented in 2021

In 2021, SERDO implemented Relief and CBT projects in Sool region as summarized below:

Location Project Type Duration Beneficiaries Fund MT Fund $
Las Anod/Buuhoodle Relief/CBT 1st April, 2021 to 30th September, 2021 2,815 1,459,296MTs $00
Las Anod/Buuhoodle Relief/CBT 1st January 2021 to 31st March, 2021 16,890    729,648MTs $00
           
           
TOTAL       2,188,944MTs 00

Projects implemented in 2020

In 2019, SERDO continued implementation of Relief and CBT projects in Sool region as summarized below:

Location Project Type Duration Beneficiaries Fund MT Fund $
Las Anod/Buuhoodle Relief/CBT 1st August 2020 to 31st December, 2021 16,890 1,469,430MTs 00
           
           
TOTAL       1,469,430MTs 00

Projects implemented in 2019

In 2019, SERDO implemented Relief and CBT projects in Sool region as summarized below:

Location Project Type Duration Beneficiaries Fund MT Fund $
Taleex/Lascanod Relief/CBT 1st Oct 2019-30 Jan 2020 16,482 1,147.147 00
Taleex/Lascanod Relief/CBT 1st June 2019-30th September 2019 16,482 00 $799,730
Lascanod/Taleex Relief/CBT 1 April 2019-30 June 2019 12,282 00 $444,780
Lascanod/Taleex Relief/CBT January-March 2019 12,282 00 $452,130
           
TOTAL       1,147.147MT $1,686,640

Projects implemented in 2018

In 2018, SERDO implemented Relief and CBT projects in Sool region as summarized below:

Location Project Type Duration Beneficiaries Fund MT Fund $
Taleex/Lascanod Relief/CBT 1 Oct-31 to Dec 2018 28,836 00 $1,376,800
Taleex/Lascanod Relief/CBT 1st July 2018 to 30th Sept 2018 28,836 00 $819,195
Lascanod/Taleex Relief/CBT 1st March 2018-30th June 2018 28,836 00 $1,093,560
Lascanod/Taleex Relief/CBT 1st Dec 2017-31 January 2018 21,426 00 $422,040
           
TOTAL       00MT $3,711,595

Projects implemented in 2017
Cash voucher unconditional distribution in Sool and Togdheer 2017 was a year of drought, only unconditional relief projects were implemented.

Location Project Type Duration Beneficiaries Fund MT Fund $
Taleex/Lascanod Cash voucher unconditional distribution 1st OCT - 31 Dec, 2017 18,300 00 $549,000
Taleex/Lascanod Cash voucher unconditional distribution 1st March - 31 Sept, 2017 18,300 00 $2,316,475
Buhodle Cash voucher unconditional distribution 1st OCT - 31 Dec, 2017 18,000 00 $549,000
Buhodle Cash voucher unconditional distribution 1st June - 31 Sept, 2017 18,000 00 $1,296,000
Buhodle Unconditional food distribution (GFD) 1st March – 30 Jun, 2017 18,000 721.8MT 00
Xudun & Taleex Unconditional food distribution (GFD) Jan-Feb, 2017 25,800 646.72Mt 00
TOTAL       1,368.52Mt $4,710,475

Projects implemented in 2016
Two types of projects were implemented a) Relief project for drought affected population: Cash voucher and food (In-kind) distribution.
b) Voucher/Food for work projects

5FFA Water catchment rehabilitationCarooley Taleex- Excavation activities, Soil embankment and Food distribution1st Jan - June, 201699699.8MT00
S/# Project Description Location Activity Duration Beneficiaries Fund MT Fund $
1 Cash Based Transfer/voucher GFD Xudun, Holhol, Lasocurdin, God’alo, Sarmanyo, Kalcad, Taleex, Dh/dhubuq, Carooley. -Cash based transfer project for drought affected communities -Duration; 1st Jan-31 Dec,2016. -Voucher value per HH: 121.59,108.5, 118.2 per month Feb – Dec 2016 25,800 00 $6,088,800
2 VFA Vegetable/ fruit/ crop production (Agricultural extension services Bocame/ Las-anod -Extension of vegetable small farm, installation of solar water pump irrigation system 1st Jan - June, 2016 4080 00 $481,440
3 FFA Water catchment rehabilitation Dabatag Las-anod - Excavation activities, soil embankment and Food distribution 1st Jan - June 2016 1824 182.8MT 00
4 FFA Water catchment rehabilitation Karin D/wayn Las-anod - Excavation activities, Soil embankment and food distribution 1st Jan - June, 2016 1824 182.8MT 00
5 FFA Water catchment rehabilitation Carooley Taleex - Excavation activities, Soil embankment and Food distribution 1st Jan - June, 2016 996 99.8MT 00
6 FFA Water catchment rehabilitation Lasocurdin Taleex - Excavation activities, Soil embankment and Food distribution 1st Jan - June 2016 990 99.2MT 00
7 FFA Road rehabilitation Kalcad Taleex - Road filling, Compacting and building drainages 1st Jan - June 2016 960 96.2MT 00
TOTAL         36,474    

Projects implemented in 2015

No. Project Description Area / Village District Beneficiaries Status
1 Check dam Qawlo Taleex 152 Completed
2 Rehabilitation of Feeder Road project Dhubudhubuq Taleex 446 Completed
3 Environmental protection- check Dam structure Holhol Xudun 303 Completed
4 Rehabilitation of Feeder Road project Geelyardeyn Taleex 305 Completed
5 Water catchment project Xudun Xudun 308 Completed
6 Water catchment project Dhaban Xudun 296 Completed
7 Environmental protection - check Dam structure Dhubuqdhubuq Taleex 303 Completed
8 Rehabilitation of Feeder Road project Gorofley Xudun 305 Completed
9 Rehabilitation of Feeder Road project Xudun Xudun 296 Completed
  TOTAL     3019  

Previous Projects implemented in 2014

No. Project Description Area / Village District Beneficiaries Status
1 Water catchment project Qawlo Taleex 347 Extended until Feb, 2015
2 Rehabilitation of Feeder Road project Laso-urdin-Basbasa Taleex 200 Completed
3 Environmental protection- check Dam construction God,alo Taleex 177 Completed
4 Rehabilitation of Feeder Road project Dameer/Taleex Taleex 376 Completed
5 Water catchment project Ballicad Buhoodle 205 Completed
6 Water catchment project Dharkeyn Buhoodle 394 Completed
7 Rehabilitation of Feeder Road project Dan Las-anod 212 Completed
8 Rehabilitation of Feeder Road project Dalyare Lasanod 401 Completed
9 Rehabilitation of Feeder Road project Karin-Dabaylweyn Lasanod 202 Extended until Feb, 2015
  TOTAL BENEFICIARIES     2514